Estimating Business Value

Business Value

Business Value is one of those terms that’s used often but rarely defined or explained.

I use “Business Value” like “Story Points”: a unit-less, relative, leading indicator of the value that will be generated when we’ve delivered the piece of the system that we’re estimating. When we’ve got this nice one-dimensional Business Value and Cost, we can quickly create a plan in two steps:

  1. Maximise delivered value by prioritising by Value/Cost
  2. Adjust the ordering to take various constraints into account: dependencies, promises that need to be honoured, risks that must be explored… This re-ordering necessarily decreases the amount of value that’s delivered, so we try to avoid dependencies, premature promises and unexplored risks that will force us to reduce value.

Estimating Business Value

But how does one estimate this mythical “Business Value”? There are a number of techniques I’ve used successfully:

  • Sort the items by value, from low to high. Don’t allow items to be given the same value, otherwise everything will end up with a high value (otherwise known as “MoSCoW Hell”). Start with the lowest value items and give them a base value, ‘100’ for example. Give all higher-valued items a relative estimate. This is exactly the same technique we use in the XP Game to teach how to estimate cost in Story Points.
  • All new items are estimated relatively to previously implemented items.
  • Build a set of representative items to estimate relatively against.
  • Don’t make your items too small. I intentionally speak of ‘items’ here, not User Stories. It’s often easier to estimate the value of a larger chunk of functionality like a Minimal Marketable Feature (MMF). When you split the item in smaller parts, divide the Business Value among them or keep the Business Value at the higher level item so that you only earn the Business Value when you implement the whole item.
  • Don’t take Business Value too seriously, it’s just a prioritisation tool.

So, we work with Business Value like with Story Points. On some projects we display this in a “burn down/up chart”. Cost burns down, while value goes up. I find this useful to break people’s (well, mostly managers’) instinctive idea that value is just the inverse of cost. Value and Cost are independent variables! It’s not because we spent 50% of the effort that we delivered 50% of the value.

The big difference between Business Value and Story Points is that I haven’t come across any company that calculated its “Business Velocity”. Velocity is measured to tie the unitless Story Points back to something tangible like man days. Velocity calibrates our story points estimates and improves its accuracy as a leading indicator of cost. Business Velocity is the same concept: if we delivered something “worth” 1000 Business Value points, how much did we actually get in something we value, like money? I have hopes that one team will actually calibrate their Business Value as that’s the business they’re in: modeling and calibrating to predict.

Improvement: build a Business Value Model

The simple process described above works well when the situation is relatively clear: one customer, one or a few sources of value that are easily identified (e.g. you sell custom software development). What if the situation is a bit more complicated? What if there are more stakeholders, each with their own definition of value? What if you value more than just money from project sales? Where does that prioritisation come from?

You build a “Business Value Model”. You make a list of all the things you value, which could include:

  • Money you get paid in the short term
  • Money you could get paid in the future (which is of course less valuable than money in the short term)
  • The happiness of your customer
  • The happiness in your company
  • New information that can be obtained
  • More visibility in the market
  • Increased reputation, prestige of the customer
  • Other sources of income
  • ….

You also list the things that you fear, that would decrease the value of what you build:

  • Technical risk
  • Market risk
  • Competition
  • ….

Select the parameters that are most important for you. Give each parameter a weight. For a start, each parameter could have the same weight. Now you can evaluate each of your projects (and maybe MMFs) against the Business Value Model to see which ones are most valuable.

The value of the Business Value Model lies not so much in the model itself but in the conversations to create and use the model. These conversations might uncover some “unspeakable” facts. For example, there might be an unspoken hierarchy among customers: those customers who have the CEO’s phone number get higher priority.

Everybody uses a Business Value Model to prioritise. You can choose to make it public or keep it unmentionable. In the companies with a Business Value Model it’s easy to see and explain why the high priority projects are high priority. Everyone knows what value they’re adding.

Playing a few rounds of the Business Value Game is a good intro to start this conversation.

The techniques above help, but estimating Business Value isn’t easy. Getting someone to estimate is like getting blood out of a stone. Doing it at or before every planning meeting takes time. What if we stopped estimating Business Value of projects, MMFs and user stories, yet retained our ability to prioritise and evaluate value delivered?

Stop estimating implementation Business Value

Project have stakeholders. Stakeholders have goals. Now, don’t ask stakeholders “What’s the value of this piece of functionality?” Ask the stakeholders: “What’s the value of achieving that goal?” What’s the value in terms of the parameters of your Business Value Model: how much new income will we generate, how much money will we save, what important information will we have gained, how will this improve our reputation and brand? We can start asking why this stakeholder needs to achieve that goal.

Now we’ve moved the conversation away from implementation issues and are firmly in business-issues land. We can value goals and their sub-goals and start prioritising them early, before we start thinking about implementation. We start the conversation about value before we can even start to talk about cost.

We can derive the required features from the goals. The business value of the features is derived from the value that’s generated when the goal is reached.

Start writing User Stories differently

I’ve found it a lot easier to start with Business Value and to derive User Stories than to create the User Stories and then add Business Value, as the conventional advice goes.

This is Agile (Business) Analysis. Continuously:

  • Create a clear vision
  • Identify the stakeholders
  • Identify their goals
  • Determine the value of the goals
  • Prioritise the goals according to value
  • Determine the capabilities needed to achieve the most important goals and to realise their value
  • “Pull” information about the needs to estimate cost, prioritise and plan
  • Let the implementers pull information about the needed capabilities
  • Track value delivered.
  • Improve the process and the model.

To reflect this process we use a different User Story format:

TO <achieve a goal>
AS A <stakeholder>

I NEED <a capability>

Liz Keogh described a similar User Story format in her blog entry about  “Feature Injection”. We start with the goal and derive the need from that.

There is one difference: we don’t use “I WANT”, but “I NEED”. When we derive capabilities from goals, we only consider those that are really needed because we use a “pull” perspective, not a “push” perspective.

Jun
01

XP Days France 2009 – a retrospective

What went well

  • Running “Miroir, gentil miroir…” for the first time in French with about 45 eager and open-minded agilistas. A great way to open the conference.
  • Meeting and talking with participants about their struggles and successes trying to become more effective.
  • The wonderful location of “La Porte Jaune” and the opportunity to go out for a bit of rowing or running.
  • Running the BusinessValue Game in French with Portia and Laurent Morisseau. Watch out for BVG v2.0 soon with French and English cards.
  • Seeing Héloise, Caroline, Didier, Laurent and Olivier from Atos Worldline presenting the good and bad experiences when we introduced Agile in their teams. Loved the “Little Red Riding Hood” fairytale theme of the “Legacy People” session.
  • The retrospective cards and the game by the “Agile Alchimists“, Jacques and François.
  • The session cards we made to describe our games. We’ll publish them soon on the Agile Coach website.
  • Relaxing before and after the conference in Vincennes and the Champs Elysées.

What went wrong

  • Missing Dominc Williams’s presentation about “Le développement hédoniste”. I’d already seen the first part of this mixture of philosophy and agility at XP Days Switzerland and I want to know how it ends. Dominic, won’t you submit this session for XP Days Benelux?
  • Except for the large auditorium the rooms were too small for such a large number of people. Luckily, we could do part of our Mirror Mirror session outside and we got a part of the dinner space to run the Business Value Game.
  • Attending too few sessions to work on our own sessions.

Puzzles

  • What was the message of the keynote “La longue défaite…” ?
  • Second-hand conflicting message about Lean vs Agile.

Lessons Learnt

  • We need to explain more during our sessions, give more context.
  • We need to limit the number of players we accept in our sessions or find a way to scale the game to more players.

Appreciations

  • To Sara Lewis and Raphaël Pierquin for helping to translate ‘Mirror, Mirror on the Wall… Why Me?’ en français
  • To Laurent Morriseau for helping to translate The Business Value Game en français
  • To the organisers for finding a great location, a smooth organisation and providing us with all we needed to run our sessions.
  • To the location staff for setting up the large room to play the Business Value Game in.

More feedback from participants and other bloggers on the Agile Coach site.